Annual Performance Plan 2015

Strategic Theme 3: Facilities Infrastructure

Establish a modern, safe work environment that emphasizes the need to maintain data quality and integrity and the importance of enhanced collaboration within the organization and with the public.


Objective 3.1: Create capacity for increased data demand.

In this Section:

The projects associated with this objective are related to the installation of the equipment necessary to run the Data Center and the migration of existing data held in the current Data Center at the Board.

Projects and Initiatives
  • Complete implementation of information technology infrastructure systems and services.
  • Complete migration of systems from the Data Center in the Board's Martin Building to the Federal Reserve Bank of Richmond's Baltimore Branch.

Back to section top


Objective 3.2: Address critical Data Center subsystem requirements.

In this Section:

Staff will work to obtain and put in place critical Data Center subsystems.

Projects and Initiatives
  • Continue the iterative space, power, and cooling analysis process for the Data Center in the Baltimore facility.
  • Perform a review of best practice measurements of data center capacity planning.

Back to section top


Objective 3.3: Create a safe and secure work environment.

In this Section:

Law enforcement staff continues to ensure that employees and visitors are adequately screened and safe while occupying a Board building. Protective measures and continuity of operations plans will be updated, where appropriate.

Projects and Initiatives
  • Complete construction of the Board's transitional law enforcement control center at the New York Avenue Building.
  • Continue the transition to a digital security system infrastructure.

Back to section top


Objective 3.4: Upgrade physical infrastructure.

In this Section:

Substantial completion of construction for the Board's offices on floors in the 1801 K Street Building occurred in 2014, with office moves scheduled for the beginning of 2015. Construction will continue on the below-grade level of the 1801 K Street Building with substantial completion of construction expected in 2015. Design work will continue on the Martin Building throughout 2015.

Projects and Initiatives
  • Continue the Martin Building renovation design.
  • Complete the remaining 1801 K Street Building leasehold improvement construction.
  • Complete the planned New York Avenue Building renovation.
  • Manage the Board's Eccles Building infrastructure enhancements and upgrades.

Back to section top


Objective 3.5: Reduce utility consumption and expenses.

In this Section:

A condition assessment of the Eccles Building was completed in 2014, analyzing the mechanical, electrical, plumbing, and architectural aspects of the building to identify possible efficiencies. In 2015, on-going assessments will ensure that existing Board facilities are operating in the same efficient manner as the Martin Building, once renovations are completed.

Projects and Initiatives
  • Review and report on energy consumption at Board-owned buildings.
  • Implement enhancements to save energy based on utility consumption versus benchmark data.